A job was budgeted to require 3 hours of labor per unit at $11.00 per hour.The job consisted of 8,000 units and was completed in 22,000 hours at a total labor cost of $269,500.What is the direct labor efficiency variance?
A) $27,500 unfavorable.
B) $22,000 unfavorable.
C) $16,000 unfavorable.
D) $22,000 favorable.
E) $6,000 unfavorable.
Correct Answer: