Multiple Choice
Zhang Industries budgets production of 300 units in June and 310 units in July.Each unit requires 1.5 hours of direct labor.The direct labor rate is $14 per hour.The indirect labor rate is $21 per hour.Compute the budgeted direct labor cost for July.
A) $6,300.
B) $6,510.
C) $9,450.
D) $9,765.
E) $16,275.
Correct Answer: