Kinetic Company Estimates That Overhead Costs for the Next Year

Question 103

True/False

Kinetic Company estimates that overhead costs for the next year will be $1,600,000 for indirect labor and $400,000 for factory utilities.The company uses direct labor hours as its overhead allocation base,and plans to use 50,000 direct labor hours for this next year.If a product uses 5 direct labor hours,then it will be assigned $200 in overhead costs.