Multiple Choice
Juarez Builders incurred $285,000 of labor costs for construction jobs completed during the month of August,of which $212,000 was direct and $73,000 was indirect supervisory costs.The correct journal entry to record the $73,000 indirect labor for the month is:
A) Debit Supervisor Wage Expense;credit Factory Wages Payable.
B) Debit Factory Overhead;credit Factory Wages Payable.
C) Debit Supervisor Wage Expense;credit Factory Overhead.
D) Debit Factory Wages Payable;credit Factory Overhead.
E) Debit Factory Wage Expense;credit Cash.
Correct Answer:

Verified
Correct Answer:
Verified
Q27: Manufacturing costs incurred for jobs completed during
Q28: A job order costing system would be
Q102: If one unit of Product Z2 used
Q105: The B&T Company's production costs for May
Q108: Drop Anchor takes special orders to manufacture
Q141: A system of accounting for production operations
Q144: Cost accounting systems used by manufacturing companies
Q150: Overapplied overhead is the amount by which
Q160: Cost accounting information is helpful to management
Q163: A job cost sheet shows information about