Multiple Choice
You are part of the team to implement new software at XYZ Inc. The employees at XYZ Inc. trust the results of the old software programs, but are cautious about accepting the outcomes of the proposed new software programs. What software implementation strategy would you recommend in this situation?
A) Direct cutover
B) Phase-in approach
C) Pilot startup
D) Parallel start up
Correct Answer:

Verified