Multiple Choice
CGI Inc. is developing a new software platform, which requires an immediate investment of $780 000 and another $260 000 in three years. Net returns expected are $450 000 after two years, $313 000 after four years, and $889 000 after six years. However, if they simply upgrade their current platform, it requires an immediate investment of $400 000, another $260 000 after two years, and $340 000 after four years. Net returns are $187 500 per year for 8 years. Determine the net present value at 5.9%. Which project is preferable according to the net present value criterion?
A) New Software platform by $53 309
B) Upgrade by $53 309
C) Upgrade by $277 277
D) New Software platform by $70 203
E) New Software platform by $76 599
Correct Answer:

Verified
Correct Answer:
Verified
Q66: An investment of $180 000 yields annual
Q67: A company has an immediate cash outlay
Q68: An obligation can be settled by making
Q69: Billy Bob wants to convert his farm
Q70: LG expects a demand of 10 000
Q72: A project requires an initial outlay of
Q73: A contract is estimated to yield net
Q74: Sean and Jessica want to sell their
Q75: Korea Nuclear tritium removal facility (TRF) project
Q76: Assume that the net present value of