Multiple Choice
Which of the following seeks to develop short range plans seeking to effectively and efficiently manage components and/or subassemblies over time period of few days to a few weeks?
A) RRP
B) MPS
C) RCCP
D) MRP
Correct Answer:

Verified
Correct Answer:
Verified