Factory Overhead for the Praeger Company Has Been Estimated as Follows

Question 49

Essay

Factory overhead for the Praeger Company has been estimated as follows: Factory overhead for the Praeger Company has been estimated as follows:   Production for the month was 90 percent of the budget,and actual factory overhead totaled $175,000. Calculate:  a.The predetermined factory overhead rate. b.The under- or overapplied factory overhead. Production for the month was 90 percent of the budget,and actual factory overhead totaled $175,000.
Calculate:
a.The predetermined factory overhead rate.
b.The under- or overapplied factory overhead.