Multiple Choice
Joshua Company prepares monthly performance reports for each department.The budgeted amounts of wages for the Finishing Department for the month of August and for the eight-month period ended August 31 were $12,000 and $100,000,respectively.Actual wages paid through July were $91,500,and wages for the month of August were $11,800.The month and year-to-date variances,respectively,for wages on the August performance report would be:
A) $200 F;$8,500 F
B) $200 F;$3,300 U
C) $200 U;$3,300 U
D) $200 U;$8,500 F
Correct Answer:

Verified
Correct Answer:
Verified
Q50: The process of establishing objectives or goals
Q51: Taylor Logan is an accountant with the
Q52: A typical factory overhead cost is:<br>A)Freight out.<br>B)Stationery
Q53: Payroll is debited and Wages Payable is
Q54: The following data were taken from Mansfield
Q56: The term "conversion costs" refers to:<br>A)The sum
Q57: The Shiplett Company's payroll summary showed the
Q58: Which of the following costs would be
Q59: When should process costing techniques be used
Q60: Witt Company maintains a continuous record of