Multiple Choice
The overhead budget, based on a budgeted volume of 100 000 direct labour hours, was $255 000. Actual overhead costs amounted to $270 000 and actual direct labour hours were 105 000. By how much was overhead under or overapplied?
A) $2250 overapplied
B) $15 000 overapplied
C) $2250 underapplied
D) $15 000 underapplied