Multiple Choice
The production of a product consists of seven work elements.The desired output rate is 2 units per minute.The work elements and their precedence relationships follow. Using the longest work-element time method,how many stations are required?
A) 2 stations
B) 3 stations
C) 4 stations
D) 5 stations
Correct Answer:

Verified
Correct Answer:
Verified