Multiple Choice
Table 3.10
You are responsible for managing a project with the following activities
(times are given in weeks) .
-Using Table 3.10,if the expected time for activity B is changed to 18 weeks,by how many weeks will the project's expected completion time increase?
A) It will not change.
B) It will increase by 1 or 2 weeks.
C) It will increase by 3 or 4 weeks.
D) It will increase by more than 4 weeks.
Correct Answer:

Verified
Correct Answer:
Verified
Q13: What options do project managers have to
Q24: An activity is the largest unit of
Q26: There are major differences between the program
Q43: Activity slack refers to how much time
Q56: The work breakdown structure is a statement
Q63: A precedence relationship specifies that one activity
Q67: A precedence relationship specifies that one activity
Q76: Activity slack is defined as:<br>A) latest start
Q84: Explain what the close out phase of
Q150: Table 3.2<br>Time (days)<br> <span class="ql-formula"