Multiple Choice
Table 4.2
High Tech, Inc. is producing two types of products: A and B. Both are produced at the same sawing operation. Because of demand uncertainties, the operations manager obtained three demand forecasts (pessimistic, expected, and optimistic) . The demand forecasts, batch sizes (units/batch) , processing times (hr/unit) , and setup times (hr/batch) follow.
The sawing machines operate on two 8-hour shifts, 5 days per week, and 50 weeks per year. The manager wants to maintain a 10 percent capacity cushion.
-Using the information from Table 4.2,if the operation currently has 18 machines and the manager is willing to expand capacity by 20 percent through short-term options,what is the capacity gap (in terms of number of machines) if you assume the optimistic demand forecasts?
A) less than or equal to 10
B) more than 10 but less than or equal to 12
C) more than 12 but less than or equal to 14
D) more than 14
Correct Answer:

Verified
Correct Answer:
Verified
Q14: Which one of the following statements about
Q20: The maximum output that a process or
Q23: The single milling machine at Fred's Manufacturing
Q53: _ is the amount of reserve capacity
Q58: How is capacity utilization calculated?
Q59: Generally, work- in- process inventory will be
Q75: The difference of 100 % - Utilization
Q84: A decision tree is a schematic model
Q132: The theory of constraints is an approach
Q138: Explain the relationship between throughput time and