Chris,a carpenter,entered into a contract with Doug for the construction of a garage on Doug's property for $5,000.Chris had constructed all of the garage,except the door,when he refused to complete the contract.
-Chris has substantially performed his part of the agreement,and would be entitled to payment of the contract price,less the amount necessary to finish the building.