Multiple Choice
Which of the following is TRUE about the critical path?
A) It has slack time in it to ensure project success.
B) A delay on the path may not delay the project.
C) It is the longest time possible to finish a project.
D) It is the shortest time possible to finish a project.
Correct Answer:

Verified
Correct Answer:
Verified
Q101: How many predecessors can an activity have?<br>A)one<br>B)none<br>C)two<br>D)unlimited
Q102: Variability in service delivery relates most closely
Q103: List and describe the elements of supply
Q104: Which of these strategies would be ineffective
Q105: Refer to the Scenario below to answer
Q107: A senior executive that indicates "if it
Q108: To improve productivity,managers must focus on people
Q109: Enhanced customer order management is achieved due
Q110: The transformation process is more evident in
Q111: List and explain some of the common