Kuczenski Corporation's cost formula for its manufacturing overhead is $45,700 per month plus $53 per machine-hour. For the month of March, the company planned for activity of 6,200 machine-hours, but the actual level of activity was 6,150 machine-hours. The actual manufacturing overhead for the month was $373,630.
-The spending variance for manufacturing overhead in March would be closest to:
A) $670 F
B) $1,980 U
C) $1,980 F
D) $670 U
Correct Answer:

Verified
Correct Answer:
Verified
Q196: Kalinowski Kennel uses tenant-days as its measure
Q197: Laboe Kennel uses tenant-days as its measure
Q198: Buffaloe Corporation manufactures and sells a single
Q199: Enriques Corporation manufactures and sells a single
Q200: Squillace Corporation uses customers served as its
Q202: Mah Clinic uses client-visits as its measure
Q203: Weisgarber Clinic uses client-visits as its measure
Q204: Fasano Clinic bases its budgets on the
Q205: Burget Clinic uses client-visits as its measure
Q206: Mulry Urban Diner is a charity supported