Multiple Choice
The Other activity cost pool is used to accumulate costs of idle capacity and organization-sustaining costs.
The company has provided the following data concerning its costs: The distribution of resource consumption across activity cost pools is given below:
The activity rate for the Order Processing activity cost pool is closest to:
A.$1,050 per order
B.$1,680 per order
C.$1,190 per order
<underLine>D.</underLine> $1,350 per order
Total Order Processing Cost:
-Laib Corporation uses an activity-based costing system with three activity cost pools.The company has provided the following data concerning its costs: The distribution of resource consumption across the three activity cost pools is given below:
How much cost,in total,would be allocated in the first-stage allocation to the Other activity cost pool?
A) $187,000
B) $133,000
C) $264,000
D) $66,000
Correct Answer:

Verified
Correct Answer:
Verified
Q7: In activity-based costing, as in traditional costing
Q10: Kleppe Corporation has provided the following data
Q36: Darter Company manufactures two products,Product F and
Q37: Whitford Corporation uses the following activity rates
Q39: The Other activity cost pool is used
Q42: The Other activity cost pool is used
Q43: The Other activity cost pool is used
Q44: Sailer Corporation uses the following activity rates
Q46: The clerical activity associated with processing purchase
Q49: Toma Nuptial Bakery makes very elaborate wedding