Multiple Choice
Which of the following statements regarding the MRP views of the material master are TRUE?
A) There are four MRP data views.
B) The system uses the MRP 4 view to select the correct BOM.
C) There are three MRP data views.
D) The system uses the MRP 3 view to determine how to procure materials make vs.buy) .
E) The system uses the MRP 1 view to select the correct BOM.
Correct Answer:

Verified
Correct Answer:
Verified