The lot size independent in-house production time is used in which of the following scenarios?
A) The lot size is fixed.
B) Processing time is constant.
C) Processing time is very short compared to the setup and interoperation times.
D) Processing time is long in comparison to the setup and interoperation times.
E) The quantity of material to be produced varies.
Correct Answer: