Multiple Choice
Setup time is the time required to
A) Set up the operations used in a work center.
B) Move materials from one work center to another.
C) Process materials in production.
D) Set up the work centers used in production.
E) Move materials from one storage location to another.
Correct Answer:

Verified
Correct Answer:
Verified