The Item Created During the SDLC That Defines the Order

Question 20

Multiple Choice

The item created during the SDLC that defines the order in which activities, tasks and jobs are to be performed, and specific check or monitoring points are established is the:


A) work breakdown structure
B) project concept
C) work packages
D) project proposal