Multiple Choice
Planning a BI implementation is a complex project and includes typical project management steps.Therefore,the first step in the BI planning process is to _____.
A) define the scope
B) define the budget
C) identify the resources needed
D) define the timeline
Correct Answer:

Verified
Correct Answer:
Verified