Multiple Choice
Skyline Builders and Pine Lumber had a contract, calling for Pine Lumber to deliver a certain quantity of bricks to Skyline's place of business on the first of every month for one year. Pine delivered the bricks one week late for the first six months, but Skyline did not object. When Pine delivered the bricks one week late, as usual, in the seventh month, Skyline attempted to cancel the contract because of the late delivery. Which of the following is true about this scenario?
A) Pine will have to return the delivery fee of the first six months because it broke the contract.
B) Skyline does not have the legal right to modify the contract.
C) Pine is not in breach because the delivery was made at the intended place of business.
D) Skyline has waived its right to cancel the contract.
Correct Answer:

Verified
Correct Answer:
Verified
Q37: Jamal purchased a motorcycle from Getaway Automobiles,
Q38: A buyer is considered to have accepted
Q39: The Uniform Commercial Code (UCC) uses the
Q40: The Uniform Commercial Code (UCC) gives the
Q41: Acceptance of goods occurs when a:<br>A) buyer
Q43: Once a party to a contract repudiates
Q44: Which of the following holds true of
Q45: Which of the following is a correct
Q46: In a sales contract, in order to
Q47: Normally, a buyer has the right to