Multiple Choice
A common pitfall in developing a master schedule for a project is a failure to:
A) understand the interdependencies among project tasks and subtasks.
B) identify all of the project tasks and subtasks.
C) correctly estimate the number of resources needed to complete the tasks.
D) correctly estimate the total time needed to complete all tasks.
Correct Answer:

Verified
Correct Answer:
Verified