Question 7

Multiple Choice

Recreational Pools,Inc. ,agrees to build a swimming pool for Sandy,but fails to build it according to the contract specifications.Sandy hires Total Fix-It Company to finish the project.Sandy may recover from Recreational Pools


A) the contract price less costs of materials and labor.
B) the contract price.
C) the costs needed to complete construction.
D) profits plus the costs incurred up to the time of the breach.

Correct Answer:

verifed

Verified