Solved

All of the Following Are Activities Performed During the Initiating/defining

Question 12

Multiple Choice

All of the following are activities performed during the initiating/defining project management phase except:


A) Stating the problems/goals
B) Securing resources
C) Writing a detailed project plan
D) Exploring costs/benefits with a feasibility study

Correct Answer: