All of the Following Are Activities Performed During the Executing

Question 26

Multiple Choice

All of the following are activities performed during the executing project management phase except:


A) Commit resources to specific tasks
B) Add additional resources/personnel if necessary
C) Writing a detailed project plan
D) Initiate project work

Correct Answer: