All of the Following Are Activities Performed During the Controlling

Question 107

Multiple Choice

All of the following are activities performed during the controlling project management phase except:


A) Create reporting tools
B) Compare actual progress with baseline
C) Establish reporting obligations
D) Writing a detailed project plan

Correct Answer: