Multiple Choice
A firm implements a new information system in one of its plants, assesses the new system's performance, and then implements the new system in its other plants. This is an example of __________ conversion.
A) Phased
B) Direct
C) Parallel
D) Pilot
E) Timely
Correct Answer:

Verified
Correct Answer:
Verified