Multiple Choice
Riverside Industries makes two products and each product is processed in three departments. The time requirements for each product in each department are given below. The profit for each product is also provided as well as the available hours in each department.
Management wants to achieve three goals. The first two goals are equal in priority.
Priority 1: Produce at least 125 units of product 1.
Priority 1: Produce at least 80 units of product 2.
Priority 2: Achieve a profit of at least 300.
-The goal programming constraint for the first goal is:
A) 3x1 + d1- - d1+ = 125
B) 3x1 - d1- + d1+ = 125
C) 1x1 + d1-- d1+ = 125
D) 1x1 - d1-+ d1+ = 125
Correct Answer:

Verified
Correct Answer:
Verified
Q37: In the _ process, the decision maker
Q38: Centerville city council is in the process
Q39: A business is trying to decide
Q40: Riverside Industries makes two products and
Q41: In scoring models, the two alternatives with
Q43: Riverside Industries makes two products and
Q44: An investor has $80,000 to invest in
Q45: The analytic hierarchy process<br>A) optimizes procedures with
Q46: Pairwise comparisons are made among<br>A) all alternatives
Q47: A production of 300 units of Twiddle