    The Activities That Must Be Completed Prior to the Start
Solved

The Activities That Must Be Completed Prior to the Start

Question 88

Question 88

Multiple Choice

The activities that must be completed prior to the start of an activity in question are called the immediate ________ of the activity in question.


A) successors
B) predecessors
C) successors and predecessors
D) followers

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q83: The diagram below shows the activities

Q84: Consider the following network.<br> <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB2836/.jpg" alt="Consider

Q85: The expected project completion time is assumed

Q86: Refer to the table below to

Q87: Consider the following project.<br> <span

Q89: When the earliest start time (ES) of

Q90: On an AOA diagram, a _ represents

Q91: Two concurrent activities in a project can

Q92: The early start for a non-critical activity

Q93: Determining project completion time is an element

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines