Multiple Choice
The activities that must be completed prior to the start of an activity in question are called the immediate ________ of the activity in question.
A) successors
B) predecessors
C) successors and predecessors
D) followers
Correct Answer:

Verified
Correct Answer:
Verified
Q83: The diagram below shows the activities
Q84: Consider the following network.<br> <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB2836/.jpg" alt="Consider
Q85: The expected project completion time is assumed
Q86: Refer to the table below to
Q87: Consider the following project.<br> <span
Q89: When the earliest start time (ES) of
Q90: On an AOA diagram, a _ represents
Q91: Two concurrent activities in a project can
Q92: The early start for a non-critical activity
Q93: Determining project completion time is an element