Solved

Consider the Following Project -What Is the Critical Path?
A) ACFG
B) ADFG
C)

Question 4

Multiple Choice

Consider the following project.
 Activity  Imunediate  Predecessor  Activity Time  (drys)   A 3B4CA4DA6EB5FC,D4GEFF7\begin{array} { | c | c | c | } \hline \text { Activity } & \begin{array} { c } \text { Imunediate } \\\text { Predecessor }\end{array} & \begin{array} { c } \text { Activity Time } \\\text { (drys) }\end{array} \\\hline \text { A } & - - & 3 \\\hline \mathrm { B } & - - & 4 \\\hline \mathrm { C } & \mathrm { A } & 4 \\\hline \mathrm { D } & \mathrm { A } & 6 \\\hline \mathrm { E } & \mathrm { B } & 5 \\\hline \mathrm { F } & \mathrm { C } , \mathrm { D } & 4 \\\hline \mathrm { G } & \mathrm { E } _ { \mathrm { F } } \mathrm { F } & 7 \\\hline\end{array}
-What is the critical path?


A) ACFG
B) ADFG
C) BEG
D) ACDFG

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions