Joe used a project management software package and has determined the following results for a given project.:
Expected completion time of the project = 22 days
Variance of project completion time = 2.77
What is the probability of completing the project over 20 days?


A) 0.3849
B) 0.8849
C) 0.1151
D) 0.7642

Correct Answer: