Multiple Choice
A PERT/CPM activity has an optimistic time estimate of 3 days, a most likely time estimate of 8 days, and a pessimistic time estimate of 10 days. The expected time (in days) of this activity is:
A) 7.0
B) 7.5
C) 8.0
D) 8.5
Correct Answer:

Verified
Correct Answer:
Verified