Multiple Choice
A PERT/CPM activity has an optimistic time estimate of 4 days, a most likely time estimate of 6 days, and a pessimistic time estimate of 10 days. The standard deviation of this activity is:
A) 7/6
B) 1/3
C) 2/3
D) 1.0