    A PERT/CPM Activity Has an Optimistic Time Estimate of 4
Solved

A PERT/CPM Activity Has an Optimistic Time Estimate of 4

Question 38

Question 38

Multiple Choice

A PERT/CPM activity has an optimistic time estimate of 4 days, a most likely time estimate of 6 days, and a pessimistic time estimate of 10 days. The standard deviation of this activity is:


A) 7/6
B) 1/3
C) 2/3
D) 1.0

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q33: Refer to the table below to

Q34: The LS and LF are calculated using

Q35: Consider the following project.<br> <span

Q36: A PERT/CPM activity has an optimistic time

Q37: The critical path is the _ path

Q39: An AON network will never require dummy

Q40: Shortening the project's duration by deleting unnecessary

Q41: Consider the following network.<br> <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB2836/.jpg" alt="Consider

Q42: In PERT, the actual project completion time

Q43: The diagram below shows the activities

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines