True/False
In a 0-1 integer programming problem involving a capital budgeting application (where xj = 1, if project j is selected, xj = 0, otherwise) the constraint x1 - x2 ≤ 0 implies that if project 2 is selected, project 1 cannot be selected.
Correct Answer:

Verified
Correct Answer:
Verified