Multiple Choice
Due to increased sales, a company is considering building three new distribution centers (DCs) to serve four regional sales areas. The annual cost to operate DC 1 is $500 (in thousands of dollars) . The cost to operate DC 2 is $600 (in thousands of dollars.) . The cost to operate DC 3 is $525 (in thousands of dollars) . Assume that the variable cost of operating at each location is the same, and therefore not a consideration in making the location decision.
The table below shows the cost ($ per item) for shipping from each DC to each region.
Region
The demand for region A is 70,000 units; for region B, 100,000 units; for region C, 50,000 units; and for region D, 80,000 units. Assume that the minimum capacity for the distribution center will be 500,000 units.
Assume that Xij = quantity shipped from distribution i to region j. i = 1,2,3 and j = 1, 2, 3, 4.
Assume that Yi = 0 or 1 where i = distribution center 1, 2 or 3.
-You have been asked to select at least 3 out of 7 possible sites for oil exploration. Designate each site as S1, S2, S3, S4, S5, S6, and S7. The restrictions are:
Restriction 1. Evaluating sites S1 and S3 will prevent you from exploring site S7.
Restriction 2. Evaluating sites S2 or S4 will prevent you from assessing site S5.
Restriction 3. Of all the sites, at least 3 should be assessed.
Assuming that Si is a binary variable, write the constraint(s) for the second restriction.
A) S2 + S5 ? 1
B) S4 + S5 ? 1
C) S2 +S5 + S4 + S5 ? 2
D) S2 +S5 ? 1, S4 + S5 ? 1
Correct Answer:

Verified
Correct Answer:
Verified
Q1: Due to increased sales, a company
Q2: Future Plastics manufactures plastic products for industrial
Q4: The branch and bound method can only
Q5: If we are solving a 0-1 integer
Q6: If we are solving a 0-1 integer
Q7: Consider the following integer linear programming
Q8: You have been asked to select at
Q9: A _ integer model allows for the
Q10: In an integer program, if building one
Q11: If we are solving a 0-1 integer