Solved

Billy's Blues Sells 3 Types of T-Shirts: Astro, Bling, and Curious

Question 75

Multiple Choice

Billy's Blues sells 3 types of T-shirts: Astro, Bling, and Curious. Manufacturing Astros requires 2 minutes of machine time and 20 minutes of labor, and costs $10. Brand Bling requires 2.5 minutes of machine time and 30 minutes of labor, and costs $14 to produce. Brand Curious requires 3 minutes of machine time and 45 minutes of labor, and costs $18 to produce. There are 300 machining hours available per week, 3750 labor hours, and he has a budget of $3000. Brand Astro sells for $15, Brand Bling for $18, and Brand Curious for $25.
The LP formulation that maximizes week profit shown below.
MAX 15A +18B + 25 C
s.t.
2A + 2.5B + 3C ≤ 300
20A + 30B + 45C ≤ 3750
10A + 14B + 18C ≤ 3000
The solution from QM for Windows is show below.
Billy's Blues sells 3 types of T-shirts: Astro, Bling, and Curious. Manufacturing Astros requires 2 minutes of machine time and 20 minutes of labor, and costs $10. Brand Bling requires 2.5 minutes of machine time and 30 minutes of labor, and costs $14 to produce. Brand Curious requires 3 minutes of machine time and 45 minutes of labor, and costs $18 to produce. There are 300 machining hours available per week, 3750 labor hours, and he has a budget of $3000. Brand Astro sells for $15, Brand Bling for $18, and Brand Curious for $25. The LP formulation that maximizes week profit shown below. MAX 15A +18B + 25 C s.t. 2A + 2.5B + 3C ≤ 300 20A + 30B + 45C ≤ 3750 10A + 14B + 18C ≤ 3000 The solution from QM for Windows is show below.        -Billy's accountant made an error, and the budget has been reduced from $3000 to $2500. Billy's profit will go down by: A)  $0 B)  $625 C)  $1350 D)  $1650
Billy's Blues sells 3 types of T-shirts: Astro, Bling, and Curious. Manufacturing Astros requires 2 minutes of machine time and 20 minutes of labor, and costs $10. Brand Bling requires 2.5 minutes of machine time and 30 minutes of labor, and costs $14 to produce. Brand Curious requires 3 minutes of machine time and 45 minutes of labor, and costs $18 to produce. There are 300 machining hours available per week, 3750 labor hours, and he has a budget of $3000. Brand Astro sells for $15, Brand Bling for $18, and Brand Curious for $25. The LP formulation that maximizes week profit shown below. MAX 15A +18B + 25 C s.t. 2A + 2.5B + 3C ≤ 300 20A + 30B + 45C ≤ 3750 10A + 14B + 18C ≤ 3000 The solution from QM for Windows is show below.        -Billy's accountant made an error, and the budget has been reduced from $3000 to $2500. Billy's profit will go down by: A)  $0 B)  $625 C)  $1350 D)  $1650
-Billy's accountant made an error, and the budget has been reduced from $3000 to $2500. Billy's profit will go down by:


A) $0
B) $625
C) $1350
D) $1650

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge