Multiple Choice
Which of the following are advantages of computer simulation over analytical methods like PERT/CPM for predicting the probability that a project will complete by a deadline?
I. It does not need to make as many simplifying assumptions.
II. It is more flexible about which probability distributions can be used.
III. It provides a solution more quickly.
A) I only
B) II only
C) III only
D) I, II, and III
E) I and II only