Customers arrive at a suburban ticket outlet at the rate of 14 per hour on Monday mornings (exponential interarrival times) . Selling the tickets and providing general information takes an average of 3 minutes per customer, and varies exponentially. There is 1 ticket agent on duty on Mondays.
What is the average number of customers waiting in line?
A) 1.633
B) 2.333
C) 2.5
D) 3.966
E) 4