Multiple Choice
Note: This problem requires the use of a linear programming application such as Solver or Analytic Solver.
The university is scheduling cleaning crews for its ten buildings. Each crew has a different cost and is qualified to clean only certain buildings. There are eight possible crews to choose from in this case. The goal is to minimize costs while making sure that each building is cleaned. The management science department formulated the following linear programming model to help with the selection process.
Min 200x1 + 250x2 + 225x3 + 190x4 +215x5 + 245x6 + 235x7 + 220x8
s.t. x1 + x2 + x5 + x7 ? 1 {Building A constraint}
X1 + x2 + x3 ? 1 {Building B constraint}
X6 + x8 ? 1 {Building C constraint}
X1 + x4 + x7 ? 1 {Building D constraint}
X2 + x7 ? 1 {Building E constraint}
X3 + x8 ? 1 {Building F constraint}
X2 + x5 + x7 ? 1 {Building G constraint}
X1 + x4 + x6 ? 1 {Building H constraint}
X1 + x6 + x8 ? 1 {Building I constraint}
X1 + x2 + x7 ? 1 {Building J constraint}
Set up the problem in Excel and find the optimal solution. Which crews are selected?
A) Crews 1, 2, and 3
B) Crews 1, 5, and 6
C) Crews 1, 7, and 8
D) Crews 2, 3, and 5
E) Crews 3, 4, and 5.
Correct Answer:

Verified
Correct Answer:
Verified
Q1: Note: This problem requires the use
Q3: In a BIP problem with 2 mutually
Q4: The algorithms available for solving BIP problems
Q5: In a BIP problem with 2 mutually
Q6: In a crew scheduling problem there is
Q7: Note: This problem requires the use
Q8: To model a situation where a setup
Q9: Note: This problem requires the use
Q10: The university administration would like to
Q11: Note: This problem requires the use