Multiple Choice
Note: This question requires access to Solver.
In the following linear programming problem, how much would the firm be willing to pay for an additional 5 units of Resource B?
Maximize
subject to (Resource A)
(Resource B)
and .
A) Nothing
B) 11.25
C) 15
D) 18.75
E) It is impossible to determine.