Note: This Question Requires Access to Solver P=3x+15yP = 3 x + 15 y

Question 34

Multiple Choice

Note: This question requires access to Solver.
In the following linear programming problem, how much would the firm be willing to pay for an additional 5 units of Resource B?
Maximize P=3x+15yP = 3 x + 15 y
subject to 2x+4y12\quad 2 x + 4 y \leq 12 (Resource A)
5x+2y105 x + 2 y \leq 10 (Resource B)
and x0,y0\quad x \geq 0 , y \geq 0 .


A) Nothing
B) 11.25
C) 15
D) 18.75
E) It is impossible to determine.

Correct Answer:

verifed

Verified

Unlock this answer now