Multiple Choice
Sahoko, the manager of a construction company, oversees allocating equipment and construction workers to different construction projects. She allocates most of the equipment and workers to high priority projects. In this scenario, Sahoko creates a ___ budget.
A) financial
B) operating
C) nonmonetary
D) zero-based
E) personal
Correct Answer: