In the __________ Phase of Project Management, the Work Defined

Question 46

Multiple Choice

In the __________ phase of project management, the work defined in the project management plan is performed to accomplish the project's requirements.


A) Completion
B) Execution
C) Initiation
D) Monitoring and control
E) Planning

Correct Answer: