Multiple Choice
Calculate the cost per unit for setup for one run of 10 000 units if setup labour is $20 per hour and 10 hours are required to set up.
A) $0.04 per unit.
B) $0.06 per unit.
C) $2.00 per unit.
D) $0.02 per unit.
Correct Answer:

Verified
Correct Answer:
Verified