Multiple Choice
Dagney was an author of a popular series of children's books. She signed an agreement with her publisher, in which she agreed to have a new book in the series written by October 15th. As noted in the contract, the timing was critical to ensuring the books would be on the shelves before Christmas and in order to coincide with a massive promotion the publisher had been planning. Faran had a terrible case of writer's block. By October 3rd, she realized that there was no way that she would have the book finished by the deadline. She e-mailed her publisher, admitting that she would not have the book finished in time. What are the publisher's options?
A) The publisher has the right to demand performance or sue.
B) The publisher cannot take any steps until October 15th, assuming Dagney does not deliver.
C) The publisher has no recourse, because Dagney's case of writer's block has made performance impossible.
D) The contract is voidable at the option of the publisher.
E) The date set out in the contract is not an enforceable term; if Dagney gets the manuscript to the publisher in a reasonable time, she will not be in breach.
Correct Answer:

Verified
Correct Answer:
Verified
Q13: Sam agreed to manufacture and supply 25
Q59: Explain what is meant by quantum meruit.
Q63: Explain how the remedy of damages is
Q107: Damages are an example of an equitable
Q116: What is the legal position of the
Q117: Discuss exculpatory (exemption) clauses and how the
Q140: The claim of frustration is not available
Q142: Which of the following is true with
Q147: Rahilly entered into a contract with Khan,
Q148: Which of the following would most likely