Question 15

Multiple Choice

If the following jobs are sequenced according to the SLACK rule then the mean tardiness (in days) for all jobs is (assume zero for today's date) If the following jobs are sequenced according to the SLACK rule then the mean tardiness (in days)  for all jobs is (assume zero for today's date)    A)  11.25 days. B)  9 days. C)  20 days. D)  12.5 days.


A) 11.25 days.
B) 9 days.
C) 20 days.
D) 12.5 days.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q2: Johnson's rule gives an optimal sequence for

Q3: A work package travels with a job

Q7: The first-come,first-served (FCFS)sequencing rule should be only

Q14: If the following jobs are sequenced according

Q17: Four products (1, 2, 3, and 4)

Q56: The shortest processing time (SPT)rule is most

Q67: The time required for a job to

Q68: Scheduling specifies when labor,equipment,and facilities are needed

Q84: _ scheduling involves loading work onto the

Q90: _ specifies when the labor,equipment and facilities

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines