Multiple Choice
Four products (1, 2, 3, and 4) must be processed on one of four machines (A, B, C, and D) . The times required in minutes for each product on each machine are shown below. The minimum time required to complete all the products is
A) 29 minutes.
B) 27 minutes.
C) 33 minutes.
D) 36 minutes.
Correct Answer:

Verified
Correct Answer:
Verified