Multiple Choice
_________________ provides the information to regulate the flow of work to and from a network of work centers.
A) A dispatch list
B) Input/output control
C) A Gantt chart
D) Drum-buffer-rope
Correct Answer:

Verified
Correct Answer:
Verified