Multiple Choice
5390. Pizazz manufactures a 5.0 oz. energy drink of the same name. Because the cans are so small, consumers are concerned that they are not receiving the full 5 ounces in each can. A quality engineer at the company is charged with analyzing the filling process and ensuring accurate readings. On 15 different occasions over the past month, she has taken a sample of 6energy drinks off the production line and recorded their weight. If the sum of the sample means is 80.20 ounces and the sum of the sample ranges is 12.68 ounces, the UCL for an X-bar chart of this process would beConsider a production process for a 5.0 oz. energy drink. A quality engineer has taken 15 samples each containing 6 energy drinks. The sum of the average of the energy drinks in the 15 samples is 80.20. The sum of the ranges of the energy drinks in the 15 samples is 12.68. The UCL for the control chart reporting variability between the sample means is
A) 5.00
B) 5.35
C) 5.76
D) 6.45
Correct Answer:

Verified
Correct Answer:
Verified
Q30: It is sometimes not necessary to determine
Q44: Attribute control charts are used to monitor
Q68: The popularity of Excel and other data
Q70: Consider a service process such as a
Q71: When calculating control limits for a process,
Q72: To monitor the number of blemishes on
Q76: A c-chart monitors the number of defects
Q77: XYZ manufacturing has received an order to
Q80: Consider a service process such as a
Q95: Process control is achieved by taking periodic